Bally's Told Regulators Parking, Utilities and Access for the A's Stadium Will Be Ready by April 2028

by Ryan Rose

Related Stories

Coyote Springs Ruling Could Cost Nevada $600M

Harry Reid Airport Tunnel Open for Thanksgiving

A's Ballpark Roof Truss and 2028 Schedule


Bally's told Nevada gaming regulators on Nov. 19 that the parking, utilities and Strip access it owes the A's new ballpark will be ready before the 2028 season. The $2.1 billion stadium is scheduled to open in April 2028 on the old Tropicana site, and the big question has been whether Bally's part of the deal would be done in time.

The promise came after a tense exchange. The Las Vegas Review-Journal reported that regulators raised concerns about Bally's commitment to the project. The Nevada Independent reported that Gaming Control Board Chairman Mike Dreitzer said he had "significant concerns" and that Las Vegas seemed to be "the bottom of the barrel" compared with Bally's other projects. Bally's Chairman Soo Kim answered that the company will meet its obligations.

The bigger shopping, dining and casino area Bally's plans around the ballpark will take years longer. Here is what was said, why the timeline matters for people who live here, and what comes next, including a Stadium Authority hearing on Dec. 3.

The A's ballpark under construction on the former Tropicana site at Las Vegas Boulevard and Tropicana Avenue in October 2026

Photo: Redspork02 / Wikimedia Commons, CC BY-SA 4.0

What Happened

On Thursday, Nov. 19, 2026, Bally's leaders went before the Nevada Gaming Control Board. The Review-Journal, in a story by Richard N. Velotta, described it as a special board meeting. The Nevada Independent, in a story by Howard Stutz, said the hearing was about Bally's purchase of a European online gaming company. Either way, the A's stadium came up, and it turned into a heated back-and-forth that the Independent said lasted about 10 minutes.

Soo Kim leads Standard General, Bally's controlling shareholder, and is Bally's chairman. According to the Review-Journal, Kim said parking, utility connections and a connection from the Strip corners to the ballpark's entrance will be ready before the 2028 season. The Independent reported that Bally's is building the northwest plaza entrance, which is the main way in from the Strip. Kim told the board Bally's would cover an initial $250 million in financial obligations for several non-gaming parts of the project. He also said there is "still plenty of time" to build the podium and the shared access that ties the plaza, stadium, utilities and parking together.

Regulators were not fully convinced. The Independent reported that Dreitzer said Bally's may be juggling too many projects and needs to be able to finish the ones it starts. That concern has context. The Independent noted that in August, Bally's used the term "going concern" in a federal securities filing about financing a $4 billion casino resort in New York City, and its chief financial officer resigned shortly after. The week before this hearing, Bally's said it lined up $500 million from lenders to finish its Chicago resort, plus a $60 million loan from Gaming and Leisure Properties.

Gaming and Leisure Properties, or GLPI, owns the 35-acre site under the ballpark and Bally's planned district. The Review-Journal reported that GLPI told the Las Vegas Stadium Authority it would increase its $125 million investment to make sure the essential infrastructure finishes on time. The Independent said that $125 million was set aside for Bally's planned $1.9 billion entertainment district, and GLPI's president, Brandon Moore, said last month the company was considering a larger loan. After the hearing, Kim told the Independent that the funding talks among Bally's, the A's and GLPI are still going and are "complicated."

On the bigger build-out, the two outlets reported slightly different timing. The Review-Journal said Bally's shops-and-restaurants area around the stadium would not be done until 2031 at the earliest. The Independent said Bally's has said it would finish its part of 27 acres of the overall development by 2030. Both agree on the main point: the full district will not be ready on opening day.

Construction of the A's ballpark on the Las Vegas Strip in February 2026, near the Tropicana Avenue and Las Vegas Boulevard intersection

Photo: DCAllStar / Wikimedia Commons, CC0 1.0

Why It Matters to Las Vegas Residents

This is not only a casino story. The ballpark is one of the biggest public-private projects in the valley, and Nevada taxpayers have money in it. KTNV reported that the Nevada Legislature set aside $380 million in public money for the ballpark. When the people responsible for parking, power and the front door are behind, everyone who helped pay for it has a reason to care.

Think about game day. KTNV reported that Bally's has to build parking garages, power systems, utilities and a plaza for opening day. If parking is short or the main entrance is not finished, the crowd still has to get in somehow. That can mean more traffic on Tropicana Avenue and Las Vegas Boulevard, more pressure on I-15 and the airport connector, and more cars spilling into nearby areas. For locals who drive through the south Strip for work, that matters on every home game night.

And there will be a lot of home game nights. A Major League Baseball team plays 81 home games a season. That is a very different rhythm from football, where the Raiders play only a handful of home games a year at Allegiant Stadium. A ballpark that is busy from spring into fall puts steady demand on parking and roads around the Strip.

Jobs and spending are part of this too. A finished district with shops, restaurants and entertainment would bring work and money to the south end of the Strip. KTNV reported that Bally's has planned a 500,000-square-foot retail, entertainment and dining district before its resort. The Review-Journal reports that area will not be done until 2031 at the earliest, and the Nevada Independent reports 2030. Either way, the ballpark could open with less around it than people expected. That affects how much nearby businesses, workers and neighborhoods benefit in the first few seasons.

Background and History

The ballpark sits at Las Vegas Boulevard and Tropicana Avenue in Paradise, on the land where the Tropicana Las Vegas stood. The Tropicana opened in 1957 and was one of the oldest resorts on the Strip. It closed in 2024 and was demolished in October 2024, according to the Independent's reporting. GLPI owns the land, and Bally's is the operator and developer of the area around the stadium.

According to Wikipedia's entry on the project, the ballpark is designed for about 33,000 seats on roughly 9 acres, with Bjarke Ingels Group and HNTB as architects. The A's broke ground on June 23, 2025. The cost has climbed over time. KTNV reported the price tag has risen to $2.1 billion, the same figure the Review-Journal used. The public share is capped at the $380 million the Legislature approved.

Bally's plans have shifted along the way. KTNV reported that an October 2024 master plan showed three hotel towers, with the first in the first phase. By September 2025, the plan showed two towers. In January, Kim said casino construction had been pushed to later phases. KTNV also reported that a Bally's representative said the casino was "unlikely" to be built by the 2028 opening, and that Stadium Authority officials had wanted Bally's to have a plan in place by August. A separate A's parking garage could cost $60 million to $100 million, KTNV reported, and a full plaza would take about 12 months to build, which is why the A's planned a temporary entrance and plaza.

Meanwhile, work on the stadium itself has kept going, as the construction photos on this page show. The A's are playing their home games at Sutter Health Park in West Sacramento while they wait for their Las Vegas home.

The Deal at a Glance

  • The ballpark: About 33,000 seats on roughly 9 acres at Las Vegas Boulevard and Tropicana Avenue, with a reported cost of $2.1 billion.
  • Opening target: April 2028, the start of the 2028 MLB season.
  • Public money: $380 million set aside by the Nevada Legislature, according to KTNV.
  • The land: GLPI owns the 35-acre former Tropicana site.
  • Bally's job: Parking, utility connections and the northwest plaza entrance from the Strip, with an initial $250 million for non-gaming parts, according to the Nevada Independent.
  • GLPI's role: A $125 million investment it told the Stadium Authority it would increase so essential work finishes on time, according to the Review-Journal.
  • The bigger district: Shops, dining and entertainment, 2031 at the earliest, per the Review-Journal, or 2030, per the Nevada Independent.
  • Next hearing: Las Vegas Stadium Authority, Thursday, Dec. 3, 2026.

What Is Confirmed and What Is Not

It helps to sort this story into two piles. The first pile is what has been said on the record. Bally's chairman told state regulators that parking, utilities and access from the Strip will be ready before the 2028 season. GLPI told the Stadium Authority it would put in more money to keep that work on time. The stadium is under construction and set to open in April 2028.

The second pile is what is still open. The final funding deal among Bally's, the A's and GLPI is not done, and Kim himself called it complicated. How much more GLPI will invest was NOT FOUND in the reporting we reviewed. The exact number of parking spaces that will be ready on opening day was also NOT FOUND. A firm date for the shops, restaurants and any casino resort has not been set, and the two news outlets gave different years for when Bally's part of the district will be finished.

Keeping those two piles separate is the best way to read every update between now and opening day. A promise made at a public hearing matters, but it is not the same as a finished garage.

The Tropicana Las Vegas resort in 2011, years before it was demolished to make way for the A's ballpark on the Strip

Photo: Michael Dorausch / Wikimedia Commons, CC BY-SA 2.0

What Happens Next

The next big date is Thursday, Dec. 3, 2026. The Independent reported that the Las Vegas Stadium Authority is expected to take up the issue at a hearing that day. Watch for whether GLPI formally raises its investment, how the three-way funding deal among Bally's, the A's and GLPI comes together, and whether the Stadium Authority asks for firmer deadlines on parking and the plaza.

After that, the clock is the story. The ballpark is scheduled to open in April 2028. That gives Bally's roughly 16 months to finish the parking, utilities and Strip access it promised. If the plaza takes about 12 months, as KTNV reported, there is not much room for delay. The A's backup plan, a temporary entrance and plaza, is a sign that planners are already preparing for a less-than-finished opening day.

There are a few signs to watch in the months ahead. One is visible work on the parking garages and the northwest plaza entrance. Another is any public update from GLPI on how much more money it will put in. A third is whether the A's announce more details about a temporary entrance. If those pieces show up on schedule, the promise Bally's made this week will look a lot more solid. If they slip, expect more tough questions from the Stadium Authority and state regulators.

Longer term, look for the retail and dining district and any casino resort to come in phases. The Review-Journal reports that work will not be done until 2031 at the earliest. The Nevada Independent reports Bally's plans to finish its part by 2030. The pace will likely depend on Bally's finances and its other projects in New York and Chicago, the same concerns regulators raised this week.

Ryan's Take

Big projects like this get people excited, and I get it. A major league team on the Strip is a big deal for Las Vegas. But when I talk with buyers and sellers, I try to keep the focus on what is actually built and what is still a plan. The stadium is going up. The parking, plaza and district around it are still being worked out. Those are two different things, and the second one is what affects daily life around the south Strip.

For most homeowners in the valley, the ballpark will not change your home's value overnight. Where it could matter is traffic and access for people who live and work near the Strip, and for owners of rental property who count on game-day demand. If you are thinking about buying near the south Strip, or in areas like Enterprise and the southwest valley because of easy access to I-15, plan for what is confirmed today. Treat the full district as a maybe for later.

A crowded minor league ballpark during a game, the kind of game day the A's hope to bring to their Las Vegas ballpark in 2028

What You Can Do

Follow the Dec. 3 Las Vegas Stadium Authority hearing. Stadium Authority meetings are public, and agendas are posted ahead of time. You can watch, read the minutes, or submit public comment if you have something to say about parking, traffic or how public money is being used.

If you live or work near the south Strip, start thinking about game-day traffic now. Learn the routes around Tropicana Avenue and Las Vegas Boulevard, and watch for road and transit plans tied to the ballpark as opening day gets closer. If you own a short-term or long-term rental near the Strip, stay on top of Clark County's rules before you count on stadium-related demand.

And if you are weighing a home purchase or sale partly because of the ballpark, talk it through with someone who watches these projects closely. A good plan looks at what is confirmed, what is likely, and what is still a hope, then builds in room for delays.

Quick Answers

Will the A's ballpark open on time? The stadium is scheduled to open in April 2028. Bally's says its parking, utilities and Strip access will be ready before that season starts.

Will the shops and restaurants be open on opening day? Probably not. The Review-Journal reports Bally's larger district will not be done until 2031 at the earliest, and the Nevada Independent reports 2030.

Why were regulators upset? The Gaming Control Board chairman said he had significant concerns that Bally's has too many projects going at once, including big resorts in New York City and Chicago.

Where is the ballpark? On the old Tropicana site at Las Vegas Boulevard and Tropicana Avenue, at the south end of the Strip.

When is the next public meeting? The Las Vegas Stadium Authority is expected to take up the issue on Thursday, Dec. 3, 2026.

Have questions about how this affects your home or neighborhood? Reach out to Ryan Rose or text/call 702-747-5921 anytime. Ryan Rose | Real Broker, LLC | 702-747-5921 | ryan@rosehomeslv.com | rosehomeslv.com

Sources

Las Vegas Review-Journal: "Bally’s promises stadium access, parking and utilities will be ready for A’s 2028 debut" by Richard N. Velotta

The Nevada Independent: "After tense exchange, Bally's chairman confirms it will build its part of A's stadium" by Howard Stutz

KTNV 13: "Bally's Las Vegas resort unlikely to open in time for A's 2028 Opening Day" by Jarah Wright

Wikipedia: New Las Vegas Stadium

Categories

Share on Social Media

GET MORE INFORMATION

Ryan Rose
Ryan Rose

Agent License ID: S.0185572

+1(702) 747-5921 | ryan@rosehomeslv.com

Name
Phone*
Message